
Muddy Boots Tour
6th October 2025
Progress continues at pace on our exciting development project. Following the completion of the brickwork in September, the roofing is nearing completion on the Hall block and is 50% complete on the Teaching block. Solar panels have also been installed on the Hall block.
Internally, the installation of insulated plasterboard to the underside of the roof has been completed in the Hall block and is nearing completion with the Teaching block. Drylining and the installation of partitions have also commenced within both buildings as have the first fix of electrics.
Looking ahead to the next month, work on the roofs to both buildings is due to be completed. Installation of the windows and doors within the Hall block will get under way, which will allow for the scaffolding to start to be removed. New water mains are due to be installed, while drylining will continue within both buildings.