Muddy Boots Tour
18th August 2025
With the new term drawing near, pupils and staff are sure to notice the rapid progress of our development project when they return to school in September.
The brickwork was only just getting under way when pupils broke up for the summer holidays but has now been fully completed on the Hall block, with only brickwork on the gables left to finish on the Teaching block.
Additional work completed over the last month has been carpentry to the roof of the Hall block, allowing the installation of roofing insulation to get under way. The parapet upstand to the gables on the Teaching block has commenced, while off-site drainage has also been completed.
Looking ahead to the next month, alongside the final stages of the brickwork, carpentry work on the roof of the Teaching block will be completed, as will insulation work on both buildings. High level ceiling works are also due to begin.