Muddy Boots Tour
13th January
The first month of construction has been busy and productive, with several key milestones completed despite the snowy and frozen conditions. The hall foundations are now finished, and important infrastructure work, including drainage and water main diversions, has been successfully completed. The site hoarding has been adjusted, and the reduced dig for the hall’s block and beam floor has been carried out. Welfare facilities for the team are also up and running.
Looking ahead to next month, work will focus on the teaching block, with foundations being laid and floor beams prepared. Steel installation will begin, and surplus soil will be removed to keep the site clear. New drainage installation will also commence. Exciting progress is being made, and we’re thrilled to continue building this amazing space!
First month timelapse with visual updates here.